Meter based PM's

I have a meter based PM that generates a work order at 50 hours. The work didn't occur until 80 hours. Does or can Maximo capture the fact we had 80 hours of operation rather than 50 when the work was performed? The only method I can find is to write down the starting meter reading and then record the meter reading at completion. I would think there has to be a method to see this in Maximo somewhere.

John
Original Post